Major roadwork’s were needed to realign the existing main airport exit road and to accommodate the change from a two lane to a four lane carriageway. This work also involved the building and integrating of a 0.5km dedicated Terminal 2 exit road.
A great amount of planning, phasing and temporary traffic management was necessary to ensure that traffic was kept flowing at all times during the works.
Key features of CHM’s service
Traffic management phasing and designs to allow for various utility diversions.
24/7 site maintenance to ensure the integrity of the temporary road layouts.
Pedestrian diversion design and implementation
CHM’s capacity to provide 24 hour daily maintenance to ensure the integrity of the temporary traffic measures.